CLIENT : PETROPARS
PROJECT DURATION : 5 MONTHS
START DATE : DECEMBER 2014
MAJOR QUANTITIES OF THE WORK:
CABLE PULLING : 13,300 M
ERECTION & COMMISSIONING & MODIFY
OF POWER DISTRIBUTION PANNEL : 10 SET
POLTETHILEN PIPING : 500 M
ERECTION & COMMISSIONING
OF TRANSFORMER : 1 SET