CLIENT : NASR CONSORTIUM
PROJECT DURATION : 14 MONTH
START DATE : Oct. 2009
DATE OF COMPLETION : March 2011
CONTRACT PRICE : 186,641,266,677 rials
MAJOR QUANTITIES OF THE WORK:
DESCRIPTION |
UNIT |
QUANTITY |
CONCRETE |
M3 |
14,000 |
FORMWORK |
M2 |
31,000 |
REBAR |
TON |
1,200 |
STEEL STRUCTURE |
TON |
1,400 |
SAND BLAST & PAINTING |
M2 |
25,000 |
BUILDING |
M2 |
14,000 |
TOTAL MANHOURS CONSUMED |
MAN HOUR |
1,598,980 |