OUR PROJECTS
EXECUTIVE OF BOILER FOUNDATION OF METHANOL UNIT OF VENIRAN APADANA PETROCHEMICAL
ERECTION OF EXTERNAL & INTERNAL OF PROCESS TOWERS OF METHANOL UNIT OF VENIRAN APADANA PETROCHEMICAL
METHANO UNIT OF VENIRAN APADANA PETROCHEMICAL
PHASE12, SOUTHPARS OFFICES AND OBSERVATION GALLARY POWER & WATER SYSTEM
Siraf Methanol Unit
EXPANSION AND UPGRADING SHAZAND ARAK REFINERY
GAS TURBINE GENERATOR UNIT 4&5 OF IRAN LNG
PHASE 12- SOUTH PARS – EPC1 – CONSTRUCTION OF NIB
PHASE 12 – SOUTH PARS – CONDENSATE TANKS
LIGHT NAPHTA HAYDROTREATING PROJECT of TEHRAN REFINERY
FOUNDATION OF ETHYLENE TANK - ILAM PETROCHEMICAL OLEFIN
SEGREGATE , PROCESS AND STORAGE OF LPG IN LAVAN ISLAND
PHASE 12. SOUTH PARS – EPC1 - PPL CAMP
Bandar Abbas gas condensate refinery renovation of Bostanoo Camp
SEGREGATE, PROCESS AND STORAGE OF LPG IN LAVAN ISLAND
KERMANSHAH CITRIC ACID PLANT
KERMANSHAH CITRIC ACID PLANT
TABRIZ PETROCHEMICAL PLANT
CONDENSATE TANKS OF PHASE 12 OF SOUTH PARS - MECHANICAL ERECTION, SAND BLAST & PAINTIN OF 4 TANKS WITH 100,000 M3 CAPACITY, ONE TANK WITH 23,000 M3 CAPACITY AND 5 UTILITY TANKS.
CLIENT : NASR CONSORTIUM
PROJECT DURATION : 24 MONTH
START DATE : Oct. 2009
DATE OF COMPLETION : Oct. 2011
CONTRACT PRICE : 8,728,464 USD
MAJOR QUANTITIES OF THE WORK:
DESCRIPTION |
UNIT |
QUANTITY |
TANK ERECTION |
TON |
8,800 |
SAND BLAST & PAINTING |
M2 |
120,000 |
TOTAL MANHOURS CONSUMED |
MAN HOUR |
1,129,910 |
More Pictures:
' ' ' ' ' ' ' ' '