CLIENT : KIMIA GHARB GOSTAR COMPANY
PROJECT DURATION : 14 MONTHS
DATE OF COMPLETION : 2006
CONTRACT PRICE : 9,500,000,000
MAJOR QUANTITIES OF THE WORK:
DESCRIPTION |
unit |
quantity |
C.S. PIPING |
INCH- DIA |
15,000 |
S.S. PIPING |
INCH- DIA |
50,000 |
EQUIPMENT ERECTION |
TON |
700 |
CABLING |
KM |
40 |
ELEC./INSTR. EQUIPMENT |
SET |
1,100 |
SAND BLASTING / PAINTING |
M2 |
10,000 |
INSULLATION |
M2 |
7,500 |
TOTAL MANHOURS CONSUMED |
MAN HOUR |
490,140 |